Completed as much as I can before the cable and phone company show up tomorrow (hopefully) to connect up service. We'll move our DirecTV when we actually move officially...
I'm a licensed North Carolina General Contractor who built a home to sell in 2008, and then built my own family home in 2014. I'm also a software engineer, marathon runner, and an occasional terrible golfer. I document my DIY experiences through this blog. ( http://wanderski.com )
Thursday, June 12, 2014
Wednesday, June 11, 2014
Shutters
We actually had shutters installed a couple weeks ago, but they screwed up and put in the wrong size. These look much better now ;-)
Also a simple irrigation system is being installed for all the new plant beds
And an update on the low voltage wiring closet
Tuesday, June 10, 2014
Low Voltage Wiring
And I thought I was close to done, hell no! :) Making good progress on LV wiring, have all 21 faceplates configured and capped now...
And making a big dent in the wiring closet in the basement. All 21 lines bundle 4 wires (2 coax, 2 cat 5e), and each cat 5e has 4 twisted pair (8 wires). This shit takes forever!
Thursday, June 5, 2014
Landscaping Continued 2
Almost done, just a few more things remaining like the brick cap on the wall, and decorative gravel on the driveway...
Sunday, June 1, 2014
Certificate of Occupancy!
2 weeks ago I had the inspector out for a final punch list, and this week he came back and checked everything. Passed!
I wish this was the end of it, but it's not. Still a lot of remaining smaller stuff to finish that wasn't critical to the CO.
I wish this was the end of it, but it's not. Still a lot of remaining smaller stuff to finish that wasn't critical to the CO.